The domestic process planning generally relies on calculations based on the construction-standard-production-rate. This method requires trial and error practice during the construction phase to deduce the optimized equipment combination for time and cost. Trial and error during construction can lead to cost overruns and schedule delays. Accordingly, this paper suggests an advanced method for establishing a productivity database based on combinations of equipment and also considering site conditions in order to reduce the timely effort for deducing the optimized equipment combination. For this purpose DES (Discrete Event Simulation) model was developed based on the information provided in the construction-standard-production-rate.