동시공학 및 LOB를 사용한 반복 프로젝트 공기단축 방법론
Crashing Method for Repetitive Project hybridizing concurrent engineering and LOB
민규태 ( Min Gyu-tae ) , 이홍철 ( Lee Hong-chul ) , 리현군 ( Li Xian-jun ) , 이동은 ( Lee Dong-eun )
UCI I410-ECN-0102-2018-500-003786936
This article is 4 pages or less.

Various methods that crash the project completion time have been studied. Line-of-Balance (LOB) is well accepted as a useful method that enables steady resource utilization without frequent hire-and-fire of resources for a project having repetitive units. Existing studies involved in LOB-CPM focuses on thesis such as resource leveling and optimization in construction scheduling community. However, crashing methods are not arrived at a full maturity in LOB scheduling, because no one handles steady resource utilization while keeping activity-relationships. This paper proposes a method that crashes project completion time by hybridizing concurrent engineering and LOB scheduling without using additional resources.